October 22, 2026
Novato has planned to rebuild Novato Boulevard between Diablo Avenue and Grant Avenue since 2001. Construction is now expected to start in late October or early November 2026 and take about 18 to 24 months. Sewer crews go first, water crews second, and the City rebuilds the surface last. That means the sidewalks, bike lanes and center turn lane people have waited a quarter century for are the final layer. Most of what drivers see in the next year will be work on pipes underneath the road.
If the start window holds, the City's own estimate puts completion somewhere between spring and late fall of 2028.
This is one combined construction job for three public agencies. The City of Novato is the lead, working with North Marin Water District and Novato Sanitary District. The City's project page says putting all the work into one project is meant to shorten construction and avoid digging up the same street over and over.
Patch reported that the work comes in three layers, and each layer is paid for differently. The funding figures come from the Marin Independent Journal's coverage of the contract vote.
| Order | Agency | What gets replaced or built | Reported funding |
|---|---|---|---|
| First | Novato Sanitary District | Sewer mains, plus the laterals that run from homes to the trunk line under the center of the street | About $4.7 million |
| Second | North Marin Water District | Water lines and the service lines to nearby houses | About $2.7 million |
| Third | City of Novato | Storm drains, bio-retention areas, traffic signals, center turn lane, bike lanes, sidewalks, driveways and landscaping | About $8.49 million in Measure AA funds for the City's share |
The Independent Journal puts the whole project at about $23.9 million, including construction, staff time and contingencies. The construction contract by itself is $16.8 million, awarded to Team Ghilotti Inc.
North Marin Water District is doing one thing that won't show up on the street. Its project page says it will install new water facilities between Diablo and Grant and leave the old pipes in the ground for possible future recycled-water use. So when the road reopens, there will be more pipe under it than there is today.
The current design dates to June 12, 2018. That's when the City Council picked a three-lane layout over a larger alternative. According to the City, the smaller footprint avoids Novato Creek, though it is still expected to remove about 28 mature trees.
PG&E's work is tied to the boulevard's schedule. The City says the boulevard project will be completed after PG&E's Rule 20A project, which moves overhead electric wiring underground along parts of the corridor. The Independent Journal reported that PG&E has been doing undergrounding and gas main work on the boulevard since 2025. The City's October 2026 update says that major work is now substantially complete. Smaller PG&E jobs will continue into 2027, including electrical service cutovers, removal of overhead equipment and telecommunications work.
The paperwork has also mostly cleared. The Council approved the contract 4-0 on August 25. A few hours before that meeting, another contractor filed a bid protest. The Council denied the protest on September 22. As of the City's October update, staff were still finalizing the construction agreement.
At the August meeting, Public Works Director Chris Benigni was direct about the experience ahead for people along the corridor. The Marin Independent Journal quoted him:
"It's going to be another 24 months of dirt, dust, noise, and I realize that the community has dealt with a lot as PG&E and the private utilities have been doing their undergrounding work for years now. But we've learned and watched and intend to communicate with the neighborhood better, have better traffic control, be less disruptive, and give well in advance notice when there's going to be major disruptions to the traffic."
Many people expect a single new cross-section from Diablo to Grant. The approved design actually changes along the way, because traffic heading north toward downtown needs more room near Seventh Street.
| Segment | Through lanes | Center lane |
|---|---|---|
| Diablo Avenue to 7th Street-Tamalpais Avenue | One in each direction | Two-way left-turn lane |
| Boulevard Terrace to 7th Street-Tamalpais Avenue | A second northbound lane is added | Two-way left-turn lane |
| 7th Street-Tamalpais Avenue to Grant Avenue | Two northbound, one southbound | Two-way left-turn lane |
Some features run the full length on both sides of the street. The City lists continuous sidewalks, Class II bike lanes, updated crosswalks and street lighting, and drought-tolerant, fire-wise landscaping. New traffic signals are planned at Diablo, Seventh and Grant. In Patch's coverage, project engineer Elisa Sarlatte said, "We are going to add sidewalks on the portions of Novato Boulevard where there currently are not sidewalks on both sides of the street."
The center turn lane solves a familiar problem. One car waiting to turn left can back up everyone behind it. Patch described the new lane as a way to pull turning vehicles out of the through lanes.
The City has not published a first-phase location, work hours or a detour plan yet. Its October update tells residents, businesses and drivers to expect periodic traffic delays, lane restrictions and temporary changes to access. The City says it will work with the contractor to keep access open wherever it can. A separate construction-information webpage with schedules and traffic impacts was expected within about two weeks of that update. In the meantime, the City's Novato Boulevard project page is where that link will appear. For questions about the PG&E work still underway, the City lists PG&E Outreach Specialist John Baston at (707) 867-9466.
The Grant Avenue end of the project includes the 2000 block of Novato Boulevard, where a lot of everyday errands happen. Sloat Garden Center is at 2000 Novato Blvd. Little Goan Indian Cafe is at 2007. Great Donuts is at 2011. FBI Burgers is at 2031 and La Carreta is at 2033. CVS is at 2035 and the Shell station is at 2085. The plan also includes rebuilt driveways along the corridor, so how you get in and out of these lots may change from week to week as crews move through.
The first weeks of work line up with the busiest stretch of the downtown calendar. Most of these events take place a block or two off the boulevard, near the Grant Avenue end of the project.
Once construction begins, it's worth checking the City's project page before any of these dates. The page will show where crews are working and whether lanes near Seventh or Grant are affected that week.
If you live, work or shop along Novato Boulevard and want to talk through how the next two years might affect a sale, a purchase or just your daily routine near the corridor, Janey Kaplan knows this part of Novato well and is glad to help. Let's Connect.
Stay up to date on the latest real estate trends.
Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact me today.